Monday, May 17, 2010

Week 5/17 - 5/21

This week we received a shipment of Drywall and insulation, we also started adding in the ventilation.
Monday: We did odd jobs around the house in order to prepare for the drywall.

Tuesday: We received the shipment of drywall and began moving it into position for the Drywall crew.

Wednesday: We continued with Tuesdays work and then we began to install the ventilation on the second floor.

Friday: We kept working on adding ventilation to the house.